[摘要]介绍了慈林医院地上大面积停车场的设计与施工过程。考虑到建筑的主入口位于建筑的2层,南侧停车场采用现浇钢筋混凝土框架体系,东侧停车场采用地上大面积堆土的形式。重点描述了大面积堆土停车场设计过程中遇到的问题和解决的办法。通过综合技术措施,控制和减小了大面积堆土停车场在施工过程中对主体结构和周边环境造成的影响。
[关键词]设计与施工; 大面积堆土; 停车场; 综合技术措施
中图分类号:TU318文献标识码:A文章编号:1002848X(2013)12002504
Design and construction of large overground car park of Cilin hospital
Zhu Baobing, Xu Xiaoming, Zhou Yuqing, Chen Zhongli
 (Shanghai Institute of Architectural Design & Research Co., Ltd., Shanghai 200041, China)
Abstract:The design and construction of large overground car park of Cilin hospital was introduced. Considering that the buildings main entrance is on the second floor, RC frame system is used in the south car park, while east car park takes the form of large soil heaping on the ground. Solutions to the problems in the design of east car park were highlighted. Through comprehensive technical measures, the impact of construction of east car park on the main structure and environment around was controlled and reduced.
Keywords:design and construction large soil heaping car park comprehensive technical measure
*上海市青年科技启明星计划项目(11QB1403200),上海建筑设计研究院青年科研基金项目(院青111类0056结)。
作者简介:朱保兵,博士,高级工程师,Emailbingbaozhu@163.com
参考文献
1]慈林医院在建项目岩土工程勘察报告[R.杭州:浙江省工程勘察院,2010.
2GB 502232008 建筑工程抗震设防分类标准[S.北京:中国建筑工业出版社,2008.
3JGJ 942008 建筑桩基技术规范[S.北京:中国建筑工业出版社,2008.
4GB 500072002 建筑地基基础设计规范[S.北京:中国建筑工业出版社,2002.
5]江正荣.地基与基础工程施工禁忌手册[M.北京:机械工业出版社, 2005.
6]刘金波.建筑桩基技术规范理解与应用[M.北京:中国建筑工业出版社, 2008.
下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!