框架-剪力墙结构中地震剪力调整方法的选用分析
赵 刚
摘 要

赵  刚
(中建国际(深圳)设计顾问有限公司,上海200235)

[摘要] 通过对大底盘多塔框架.剪力墙结构中各塔楼框架部分的地震剪力调整的深入分析研究,阐述了实际工程设计过程中应如何正确把握对规范条文的理解,指出设计人员容易忽略的问题,为解决类似问题提供了一定的工程经验。
[关键词] 大底盘多塔;框架-剪力墙结构;地震剪力调整

Reasonable adjustment of earthquake-shearing-force in frame-shearwall structure
Zhao Gang
(China Construction (Shenzhen) Design Intemational Co., Ltd., Shanghai 200235, China)

Abstract: Studies have been made on the adjustment of the earthquake-shearing-force of the framework of each tower in frame-shearwall structure with several towers based on one big chassis. It shows the right methods to understand the codes and also points out the problems easily to be ignored in practice. Such engineering experiences are really useful in engineering design to solve similar problems.
Keywords: several towers based on one big chassis; frame-shear wall structure; adjustment of earthquake-shearing-force