- 摘 要
-
肖昌飞,冯海华
(广东南海建筑设计院有限公司第一分公司,佛山528200)[摘要] 本文主要从钢筋与混凝土的受力角度来阐述纵向受力钢筋的搭接位置与搭接长度,进而对《混凝土结构工程施工质量验收规范> (GB50204-2002)及《混凝土结构施工图平面整体表示方法制图规则和构造详图》( 03G101-1)(未修正版)及(修正版)中几个关于钢筋搭接的问题进行了探讨,并提出了相应的改进措施。
[关键词] 钢筋搭接;搭接位置;搭接长度;措施Discussion about lap splicing of reinforcement
Xiao Changfei, Feng Haihua
(The First Branch Company of Guangdong Nanhai Architectural Design Institute Co., Ltd, Foshan 528200, China)Abstract: Based on the bond force between reinforcement and concrete, the lap location and the length ofreinforcement are elaborated. Compared the national standard drawing 03G101-1 with the national standard Code for Acceptance Of Constructional Quality of Concrete Structures GB50204-2002, several questions on lap splicing of reinforcement are discussed and corresponding improvement measures are given.
Keywords: reinforcement; lap splicing; lap location; lap length; measure