某厂房加固改造设计
郭丽峰1,孙苍柏2,陈为民1
摘 要

郭丽峰1,孙苍柏2,陈为民1
(1 包钢集团设计研究院,包头014010; 2 包钢集团无缝厂,包头014010)

[摘要] 延长厂房增加吊车并利用旧有厂房,要求对旧有厂房钢筋混凝土双肢柱加固并增加吊车肢。本文对加吊车肢柱子进行模型简化,可以直接利用PKPM软件进行计算。新开挖设备基础埋深远超过原有柱基础,施工采用桩基础支护达到要求。
[关键词] 加固;计算;桩基础支护

    Strengthening and reconstruction of an existing factory building
   
Guo Lifeng1,  Sun Cangbai2,  Chen Weimin1
    (1 The Design And Research Institute Of Baotou Iron And Steel Group, Baotou 014010, China; 2 Seamless (Steel) Tubing Mill Of Baotou Iron And Steel Group, Baotou 014010, China)

Abstract: Combined with a project, this paper elaborates a simply calculating method for column strengthening of the old factory by PKPM software .The calculated column to support crane loads was combined zigzag interconnected cement bars old reinforced concrete column with steel pillars. In this paper, equipments foundation depth was far ahead adjacent old building column base. We pay a choice of piled foundation protect in this deep foundation ditch to solve the problem.
Keywords: strengthening; calculation; piled foundation protect