- 摘 要
-
王为群1,刘亚宇1,王 强1,曹云锋1,冯 云2
(1 中国纺织工业设计院,北京100037;2 中材地质工程勘察研究院,北京100102)[摘要] 在滁州市某聚酯工程中,采用载体桩技术与CFG桩法相结合,取其各自优点,发展成新的地基处理方法——载体桩复合地基。该方法既能充分发挥桩问土的承载力,又能缩短桩长、减少地基的变形,与其他的桩基础设计相比,可缩短工期、降低投资成本。
[关键词] 载体;三击贯入度;褥垫层;复合地基Design of composite foundation with composite bearing base and cement-flyash-graved pile
Wang Weiqun1, Liu Yayu1, Wang Qiang1, Cao Yunfeng1, Feng Yun2
(1 China Textile Industrial Engineering Institute, Beijing 100037, China; 2 Zhongcai Geo-engineering Exploration Institute)Abstract: A new technology of ground treatment that adopted the advantages of both ram-compaction piles with composite bearing base and cement-flyash-graved piles was introduced. This technology developed the method of ground treatment. The author introduced the principles and method of design for ram-compaction piles with composite bearing base and cement-flyash-graved pile, and how form composite foundation, and single pile bearing capacity and characteristic value of composite foundation bearing capacity and calculation of settlement were introduced detailedly.
Keywords: composite bearing base; depth of three beat; bedtick layer; composite foundation