- 摘 要
-
陈海洲1, 王玉岭1, 刘进贵1, 王桂玲1, 徐 伟2
(1 中国建筑第八工程局有限公司,上海200120;2 同济大学土木学院,上海200092)[摘要] 在介绍超高层钢结构建筑施工模拟分析的理论的基础上,阐述了对钢框架.混凝土核心筒结构的结构体系的施工模拟分析的方法。运用ETABS9.2版本软件的运行施工顺序加载分析模块对大连裕景ST1塔楼进行了第一段(B-4~ S14层)的施工模拟分析。通过施工模拟分析的结果,能够找出核心筒和外框柱的变形差异,为工程钢结构构件的加工和安装提供指导。
[关键词] 超高层;钢结构;结构体系;施工模拟;施工顺序加载
中图分类号:TU974 文献标识码:A 文章编号:1002-848X(2011) Sl-0821-04Construction analog simulation theory and technology on super high-rise steel building
Chen Haizhou1, Wang Yuling1, Liu Jingui1, Wang Guiling1, Xu Wei2
(1 Cluna Construction Eighth Engineering Division Co., Ltd., Shanghai 200120, China; 2 School of Civil Engineering, Tongji University, Shanghai 200092, China)Abstract: Based on the introduction of the analog simulation theory of the super high-rise building, explained scientifically the analog simultion technology on the the steel frame-concrete corewall nuxed structure system. By use the modul of constuction sequential add load analysis of the ETABS 9.2, analyzed the floor from B-4 t0 14th of the main structure. Calculated some datum and find out the deviation between the outer frame collumn and core tube wluch can provide some experiences to the construction and fabrication of the steel member of the project.
Keywords: super high-rise building; steel structure; structure system; construction analog simulation; sequential add load