- 摘 要
-
(1 河北工业大学土木与交通学院, 天津 300401; 2 河北省建筑科学研究院有限公司, 石家庄 050021)
[摘要]目前纠倾技术主要依靠过去经验来指导工程实践,以往的纠倾对象多为多层和低层建筑,高层建筑纠倾尚未形成系统的理论和设计施工体系。采用ABAQUS软件模拟某高层基础少倾侧开挖卸荷沟纠倾技术实施情况,得出卸荷沟最优深度为20~25m,与建筑最优距离为1m。建议卸荷沟开挖厚度为0-2m,与建筑边缘距离为1m,开挖宽度为20m,开挖深度为15m。
[关键词]高层建筑; 纠倾研究; 有限元模拟; 卸荷沟法
中图分类号:TU746-3文献标识码:A文章编号:1002-848X(2019)08-0130-06
Finite element analysis of excavation unloading ditch method for rectification on less inclined side of high-rise building foundation
Fu Shifeng1,2, Rong Xian1, Li Yurun1
(1 School of Civil and Transportation Engineering, Hebei University of Technology, Tianjin 300401, China; 2 Hebei Academy of Building Research Co., Ltd., Shijiazhuang 050021, China)
Abstract:At present, the rectification technology mainly relies on the past experience to guide the engineering practice. In the past, the object of rectification is mostly multi-storey and low-rise buildings, and there is no systematic theory and design and construction system for high-rise buildings. ABAQUS finite element software was used to simulate the implementation of excavation unloading ditch method for rectification on less inclined side of high-rise building foundation to find the optimal depth of the unloading ditch is 20~25m and the optimum distance from building is 1m. It is suggested that the excavation thickness is 0-2m, the excavation distance is 1m, the excavation width is 20m and the excavation depth is 15m.
Keywords:high-rise building; rectification research; finite element simulation; unloading ditch method
作者简介:付士峰,博士研究生,高级工程师,Email: 18033878005@163.com。