您现在的位置:建筑结构>> 期 刊>> 2016年>> 第21期>>正文内容
华策国际大厦结构修改设计
张立平,徐卫,黄瑞瑜
摘 要

(广东省建筑设计研究院, 广州 510010)

[摘要]介绍了华策国际大厦结构设计修改情况。对主楼地上结构修改设计前后地震反应进行了比较,对修改设计后采用半逆作施工的情况和采用的新型钢板剪力墙及空中连廊先铰后刚设计方法这两项关键技术进行了介绍和分析。分析结果表明,修改设计不仅提高了构件制作标准化和安装机械化程度,加快了施工速度,一些关键性能指标还得以改善,可以为类似工程提供参考。

[关键词]华策国际大厦; 修改设计; 半逆作施工法; 外包钢板-混凝土组合剪力墙; 先铰后刚

中图分类号:TU318, TU398文献类型:A文献标识码:A文章编号:1002-848X(2016)21-0046-05

 

Modified structural design of Huace International Building

Zhang Liping, Xu Wei, Huang Ruiyu

(Architectural Design and Research Institute of Guangdong Provine, Guangzhou 510010, China)

Abstract:The modified structural design of Huace International Building was presented. The seismic responses of the upper structure of main building before and after modification were compared. In the process of modified design, semi-reversed construction method was introduced. Two key technologies were introduced and analyzed including the adoption of new steel plate shear walls and the design method of the overhead corridor with stiff connection after hinged connection. Analysis results show that the modified design not only develops the standardization degree for component production and the mechanization degree for installation, but also accelerates construction speed, and some key performance indicators were improved, which can provide a reference for similar projects.

Keywords:Huace International Building; modified design; semi-reversed construction method; composite shear wall with outsourced steel plate; stiff connection after hinged connection

 

作者简介:张立平,硕士,高级工程师,Email:zlpzhang@sina.com。

下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!