您现在的位置:建筑结构>> 期 刊>> 2016年>> 第19期>>正文内容
某框剪结构隔震支座顶升更换试验研究
叶烈伟,邓烜,蒋航军
摘 要

(中国建筑标准设计研究院, 北京 100048)

[摘要]对某隔震结构支座顶升更换试验进行了介绍,包括主体结构内力分析、变形差预测、结构顶升、支座更换及安装。其中顶升方案采用的是异步顶升法,并详细介绍了异步顶升法的设计及关键技术,主要包括异步顶升法的传力装置、顶升器的布置以及竖向位移控制体系等,同时对异步顶升法进行了经济分析。

[关键词]隔震; 支座更换; 异步顶升; 经济分析

中图分类号:TU352-1+2文献标识码:A文章编号:1002-848X(2016)19-0083-05

 

Experimental study on jacking-up replacement of isolation bearing for a frame-shear wall structure

Ye Liewei,  Deng Xuan,  Jiang Hangjun

(China Institute of Building Standard Design & Research,  Beijing 100048,  China)

Abstract:The jacking-up replacement test of the bearing of an isolation structure was introduced,  including the internal force analysis of the main structure,  the prediction of the deformation difference,  the jacking-up of the structure,  the replacement and installation of the bearing. The jacking-up scheme adopted asynchronous jacking-up method,  and the design and key technologies of asynchronous jacking-up method were introduced including arrangement of force transmission device and jacking-up machine and the vertical displacement control system in asynchronous jacking-up method. And the economic analysis was carried out on asynchronous jacking-up method.

Keywords:isolation; bearing replacement; asynchronous jacking up; economic analysis

 

作者简介:叶烈伟,硕士,助理工程师,Email: yeliewei@qq.com。

下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!