您现在的位置:建筑结构>> 期 刊>> 2016年>> 增刊S2>>正文内容
双回路超高压电缆浅埋暗挖隧道断面优化设计*
魏志强,陈孝湘
摘 要

(福建省电力勘测设计院, 福州 350003)

[摘要]根据现有的技术手段,在软土地区修建专用电缆隧道一般采用顶管法或盾构法,而在硬质岩地区则选用浅埋暗挖法。一般情况下,电缆隧道周边的构筑物或管线对地层变形允许值要求都比较高,当浅埋暗挖电力隧道采用国家电网公司推荐的直墙拱形断面时,隧道施工引起的周边地层变形都较大,实施过程往往需要迁改地下管线。在对双回路超高压电力电缆空间需求分析的基础上,优化隧道内的电缆及其附属设施的布置方案,而后采用三心圆法绘制曲墙拱形的浅埋暗挖隧道断面;与此同时,采用数值分析方法对隧道施工过程引起的周边地层变形进行模拟。分析结果显示:采用三心圆形法的隧道断面较直墙拱形隧道断面减小周边地层变形量达15%以上,带来了良好的环境效益;研究结果指导工程建设,并为类似工程建设提供参考。

[关键词]双回路; 超高压电缆; 暗挖隧道; 曲墙拱形隧道; 优化设计

中图分类号: TU94,TU457 文献标识码: A文章编号:  1002-848X(2016)S2-0564-05

 

Optimal design of the shallow buried covered excavation tunnel which used double circuit EHV cable transmission lines

Wei Zhiqiang, Chen Xiaoxiang

(Fujian Electric Power Survey & Design Institute, Fuzhou 350003, China)

Abstract: As common technology, the pipe jacking method or the shield method has been used usually in the tunnel construction in the soft clay district, and the shallow buried covered excavation method is been application in the hard rock district. The environment of the EHV cable tunnel is usually full of pipe lines or underground structures, which require high of the deformation cased by the tunnel excavation. According to the experience of the shallow buried excavation tunnel, the deformation has a great chance to go beyond the design control value, which makes a lot of pipe lines or the underground structures have to be modified. Based on space requirement anlysis of two extra high voltage cable lines, arrange the cable and the ancillary facilities inside the tunnel was optimized, and then the tunnel cross section into arc sidewall by three circle method was drawed, finialy, the deformation caused by the tunnel excavation was simulated by finite element method. The simulation results show that, the three circle method tunnel could reduce the deformation into 15% of the straight sidewall, which takes great environment benefits. The research can guide the design of the tunnel design and provide references for similar construction.

Keywords: double circuit; EHV cable; covered excavation; arc side wall tunnel; optimal design

 

作者简介: 魏志强,一级注册结构工程师,副总工程师,Email:Weizq@fedi.cn。

 

*中国电力建设股份有限公司科技项目(No.DJ-ZDXM-2014-28)。

下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!