您现在的位置:建筑结构>> 期 刊>> 2009年>> 第03期>>正文内容
振动沉管法CFG桩加固含硬夹层软弱地基及其检测评价
刘志杰,王后裕,刘启川
摘 要

(空军工程设计研究局,北京 100068)
[摘要]针对某一工程特殊的地质条件和对地基的具体要求,采用CFG桩复合地基,并对施工方面可能出现的问题进行了分析,提出了具体的解决措施。现场载荷试验及反射波法低应变动力检测试验表明,CFG桩桩身完整性很好,复合地基的承载力提高显著,证明该工程的CFG桩复合地基设计及施工是成功的。
[关键词]CFG桩复合地基;振动沉管法;现场载荷试验;低应变动力检测
Treatment of weak ground intercalated rigid layer by vibrating tubular CFG pile and its monitoring test
Liu Zhijie,Wang Houyu,Liu Qichuan(Air Force Engineering Design & Research Bureau, Beijing 100068, China)
Abstract:CFG pile composite foundation is applied in a project according to its special demand and characteristic geological condition. The problems that might be met in construction are analyzed and the corresponding detail measures are presented. The results of plate loading test and low strain dynamic testing show that the quality of CFG pile composite foundation is good and subgrade bearing capacity has been improved successfully.
Keywords:CFG pile composite foundation; vibrating tubular; plate loading test; low strain dynamic testing
作者简介:刘志杰,高级工程师,一级注册结构工程师,一级注册建筑师,Email:luckmanwang@yahoo.com.cn。
参考文献
[1]GB5007—2002建筑地基基础设计规范[S].
[2]JGJ79—2002 建筑地基处理技术规范[S].
[3]关伟兰,等. CFG桩复合地基在国美家园工程中的应用[J]. 建筑结构,2007,37(11).