天津西站北广场地下工程结构设计
徐壮涛
摘 要

(上海市城市建设设计研究总院,上海 200125)

 

 [摘要] 天津西站北广场地下工程为超长半地下结构,设计中同时面临了地铁区间段下穿形成的大跨结构,以及结构净高的严格控制。通过采用短向受力框架体系、温度效应分析、预应力设计等手段,综合解决了上述设计问题,相关方法与思路可为同类型结构设计提供参考。

[关键词] 超长;地下结构;结构布置;温度效应;预应力

中图分类号:TU318

 

作者简介:徐壮涛,

 

Structure design on north square of Tianjin west railway station underground structure

Xu Zhuangtao

(Shanghai Urban Construction Design & Research Institute, Shanghai 200125, China)

Abstract: North square of Tianjin west railway station underground structure is a semi-underground structure, of which the long span structure over metro section and the clear space should be considered in design. Design difficulties were successfully solved by adopting short-direction-supported frame system, temperature effect analysis, prestressed concrete design method. The design methods adopted in this project can provide reference for the similar structure design.

 

Keywords: super long; underground structure; structural arrangement; temperature effect; prestressed

 

                        参考文献

[1] 王铁梦工程结构裂缝控制[M].北京:中国建筑工业出版社,1997

[2] 郑振鹏.天津西站超长混凝土结构温度应力分析[J].中国市政工程,201084-85,99