您现在的位置:建筑结构>> 期 刊>> 2015年>> 第01期>>正文内容
深圳北站站台雨棚新型弦支屋盖张拉模拟及试验研究*
孙璨1,傅学怡2,吴兵2,冯叶文2,孟美莉2,袁行飞3
摘 要
(1 东莞理工学院建筑工程系, 东莞 523808; 2 深圳大学建筑设计研究院, 深圳 518060;3 浙江大学空间结构研究中心,杭州 310058)
 
[摘要]针对深圳北站站台雨棚屋盖采用的由四边形环索、竖向撑杆、斜杆及上部柱面网壳构成的弦支结构体系,结合其结构形式及工作特性,提出了适于该结构体系的基本张拉方法、模拟算法及施工方案,并通过缩尺模型试验开展了3×3跨弦支单元体系的施工张拉模拟验证,进而确定了该站台雨棚屋盖整体结构施工张拉的控制原则和总体方案。全过程施工张拉模拟分析对比表明,提出的张拉方法、步骤及预应力控制方案等能确保施工张拉全过程及张拉完成后该新型弦支结构体系的强度、刚度及稳定性始终符合设计要求,并保持安全稳定。
[关键词]深圳北站; 雨棚; 四边形环索; 施工张拉; 试验
中图分类号:TU248.1,TU394      文献标识码:A      文章编号:1002-848X(2015)01-0053-05
 
Pre-stressing simulation and experimental study of new type suspended roof in platform canopy of Shenzhen North Railway Station
Sun Can1, Fu Xueyi2, Wu Bing2, Feng Yewen2, Meng Meili2, Yuan Xingfei3
(1 Department of Civil Engineering, Dongguan University of Technology, Dongguan 523808, China; 2 The Institute of Architecture Design & Research, Shenzhen University, Shenzhen 518060, China; 3 Spatial Structure Research Center, Zhejiang University, Hangzhou 310058, China)
 
Abstract: The platform canopy of Shenzhen North Railway Station adopts a new-type suspended structural system composed of quadrilateral hoop cable elements, vertical brace struts, inclined struts and top cylindrical lattice shell. Combined with the structure form and working characteristics, the basic pre-stressing method, simulation algorithm and construction scheme were proposed suitable for this structural system, and the construction pre-stressing simulation verification was carried out by scale model test of 3×3 span suspended element system. And then the control principle and general scheme of construction pre-stressing of the whole structure of platform canopy roof was confirmed. The comparison analyses of whole process simulation of construction pre-stressing indicate that the proposed method, step and pre-stressed control schemes can ensure the design requirements of strength, stiffness and stability of the new-type suspended structural system in whole construction pre-stressing process and completion.
Keywords: Shenzhen North Railway Station; canopy; quadrilateral hoop cable; construction prestressing; experiment
*国家自然科学基金项目(90715012,51308117)。
通讯作者:傅学怡,研究员,Email:fu_xue_yi@aliyun.com。
 
参考文献
[1]陈志华.弦支结构体系研究进展[J].建筑结构,2011,41(12):24-31.
[2]郭佳民,袁行飞,董石麟,等.弦支穹顶施工张拉全过程分析[J]. 工程力学,2009,26(1):198-203.
KANG W J, CHEN Z, LAM H F. Analysis and design of the general and outmost-ring stiffened suspend-dome[J]. Engineering Structure, 2003, 25(2): 1685-1695.
[4]KITIPORNCHAI, KANG W J, LAM H F, et al. Factors affecting the design and construction of lamella suspen-dome systems[J]. Journal of Construction Steel Research, 2005, 61(6): 26-30.
[5]李志强,张志宏,袁行飞,等.济南奥体中心弦支穹顶结构施工张拉分析[J]. 空间结构,2008,14(4):14-20.
[6]张国军,葛家琪,秦杰,等. 2008奥运会羽毛球馆弦支穹顶预应力张拉模拟施工过程分析研究[J].建筑结构学报,2007,28(6):31-38.
[7]庞礴.弦支柱面网壳的理论分析与试验研究[D].杭州:浙江大学,2010.
[8]浙江大学空间结构研究中心.深圳北站站台雨棚结构缩尺模型试验报告[R]. 2009.