您现在的位置:建筑结构>> 期 刊>> 2007年>> 第11期>>正文内容
北京银泰中心塔楼桩基础设计
李培彬,赵广鹏,娄宇,韩合军,吕佐超,黄健
摘 要
(中国电子工程设计院,北京100840)
[提要]北京银泰中心工程地面建筑由一座酒店、两座办公楼和三座裙房组成,地下为长218.2m,宽99.2m的整体4层地下室,所有地上建筑都坐落在整体地下室的顶部。工程基础底面受力极不均匀,各栋建筑对沉降的不均匀性十分敏感,且基础工程量巨大,对工程总投资和工程进度都有较大影响,因此,工程在基础选型、持力层和桩径的选取、新技术的采用以及施工监测方面都做了较充分的方案论证和分析计算,所做工作为整个工程的顺利竣工打下了坚实的基础。
[关键词]差异沉降;静载试验;沉降后浇带;桩端桩侧后压浆技术
Pile Foundation Design of Towers of Beijing Yintai Center/Li Peibin, Zhao Guangpeng, Lou Yu, Han Hejun, Lü Zuochao, Huang Jian(China Electronics Engineering Design Institute, Beijing 100840, China)
Abstract:Beijing Yintai Center project is composed of a restaurant, two office buildings and three assistant buildings. All the buildings are based on four floors basement structure which is 218.2m long and 99.2m wide. The loads on base are changed greatly and each building is sensitive to asymmetric settlements. The structure design gets sufficient project argumentation and computing in selecting type of base, confirming the right bearing load earth layer and diameters of piles, using new technology and inspecting construction.

Keywords:differential settlement; static load test; settlement strip of post cast concrete; post pressure grouting technology

下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!